On the road to the village of Elitnoye, the installation of a leveling layer of asphalt concrete has been completed
On the road to the village of Elitnoye from the Kharkiv-Vovchansk highway to the Kharkiv ring road, work has been completed on the installation of a leveling layer of asphalt concrete mixture on two repair sections with a total length of 3.5 km.
In total, this year, it is planned to repair 15 km of road surface on this road from the state-owned road Kharkiv-Vovchansk to the village of Sorokivka.
To date, work on the installation of a two-layer road surface has been fully completed on the section from the ring road to the settlement of Sorokivka. Currently, work on the installation of landing pads and car pavilions is continuing.
On the section from the Kharkiv-Vovchansk highway to the ring road, work is being carried out on the installation of curbstones, after which work will be carried out on the installation of the upper layer of the surface.
At the final stage, in accordance with the project documentation, work will be carried out to strengthen the roadsides, install access pockets and landing areas for public transport stops, replace existing car pavilions, install barrier fencing on dangerous sections of the road, install road signs and guidance devices (signal columns), and apply horizontal road markings.